Action Date | Action Description |
---|---|
Jan 05, 2017 | Preliminary Determination Request (Coastal) |
Jan 05, 2017 | Application Accepted |
Jan 05, 2017 | Team Review for Completeness |
Jan 13, 2017 | HPHC Historical Preservation No Effect |
Jan 23, 2017 | Additional Information Received |
Feb 06, 2017 | Additional Information Received |
Feb 08, 2017 | Typist for Processing |
Feb 08, 2017 | Category A assigned |
Feb 08, 2017 | Executive Sign Off |
Feb 08, 2017 | Sent to Photo Copy |
Feb 08, 2017 | Permit Approved |
Feb 08, 2017 | Biologist Report |
Feb 16, 2017 | Land Evidence Date |
Mar 29, 2018 | Modification Request |
Mar 30, 2018 | Administrative Review for Completeness |
Mar 30, 2018 | Team Review for Completeness |
Mar 30, 2018 | Application Accepted |
Apr 06, 2018 | Biologist Report |
Apr 09, 2018 | Typist for Processing |
Apr 09, 2018 | Executive Sign Off |
Apr 09, 2018 | Sent to Photo Copy |
Apr 09, 2018 | Modification Approved |
Apr 11, 2018 | HPHC Historical Preservation No Effect |
Apr 23, 2018 | Land Evidence Date |
May 22, 2019 | Additional Information Received |
Jun 10, 2019 | Letter of Authorization |
Oct 21, 2019 | Modification Request |
Oct 22, 2019 | Eng Team Review for Completeness |
Oct 22, 2019 | Engineering Report |
Oct 22, 2019 | Biologist Report |
Oct 22, 2019 | Application Accepted |
Oct 22, 2019 | Typist for Processing |
Oct 22, 2019 | Executive Sign Off |
Oct 22, 2019 | Sent to Photo Copy |
Oct 22, 2019 | Modification Approved |
Oct 28, 2019 | Modification Request |
Oct 28, 2019 | Land Evidence Date |
Oct 31, 2019 | Bio Team Review for Completeness |
Nov 05, 2019 | Biologist Report |
Nov 05, 2019 | Typist for Processing |
Nov 05, 2019 | Executive Sign Off |
Nov 05, 2019 | Sent to Photo Copy |
Nov 05, 2019 | Modification Approved |
Nov 07, 2019 | HPHC Historical Preservation No Effect |
Jan 14, 2020 | Land Evidence Date |
Jul 09, 2021 | Modification Request |
Jul 12, 2021 | Administrative Review for Completeness |
Jul 14, 2021 | Eng Team Review for Completeness |
Jul 14, 2021 | Project Manager |
Jul 16, 2021 | Engineering Report |
Jul 16, 2021 | Letter of Authorization |
Jul 19, 2021 | Land Evidence Date |
Jul 21, 2021 | HPHC Review Pending |
Jul 21, 2021 | HPHC Historical Preservation No Effect |
Jan 27, 2022 | Modification Request |
Jan 31, 2022 | Administrative Review for Completeness |
Feb 11, 2022 | Project Manager |
Feb 11, 2022 | Bio Team Review for Completeness |
Feb 15, 2022 | Biologist Report |
Feb 15, 2022 | Typist for Processing |
Feb 15, 2022 | Executive Sign Off |
Feb 15, 2022 | Sent to Photo Copy |
Feb 15, 2022 | Letter of Authorization |
Feb 18, 2022 | Permit Mailed |
Apr 07, 2022 | Land Evidence Date |