Jan 05, 2017 Preliminary Determination Request (Coastal)
Jan 05, 2017 Application Accepted
Jan 05, 2017 Team Review for Completeness
Jan 13, 2017 HPHC Historical Preservation No Effect
Jan 23, 2017 Additional Information Received
Feb 06, 2017 Additional Information Received
Feb 08, 2017 Typist for Processing
Feb 08, 2017 Category A assigned
Feb 08, 2017 Executive Sign Off
Feb 08, 2017 Sent to Photo Copy
Feb 08, 2017 Permit Approved
Feb 08, 2017 Biologist Report
Feb 16, 2017 Land Evidence Date
Mar 29, 2018 Modification Request
Mar 30, 2018 Administrative Review for Completeness
Mar 30, 2018 Team Review for Completeness
Mar 30, 2018 Application Accepted
Apr 06, 2018 Biologist Report
Apr 09, 2018 Typist for Processing
Apr 09, 2018 Executive Sign Off
Apr 09, 2018 Sent to Photo Copy
Apr 09, 2018 Modification Approved
Apr 11, 2018 HPHC Historical Preservation No Effect
Apr 23, 2018 Land Evidence Date
May 22, 2019 Additional Information Received
Jun 10, 2019 Letter of Authorization
Oct 21, 2019 Modification Request
Oct 22, 2019 Eng Team Review for Completeness
Oct 22, 2019 Engineering Report
Oct 22, 2019 Biologist Report
Oct 22, 2019 Application Accepted
Oct 22, 2019 Typist for Processing
Oct 22, 2019 Executive Sign Off
Oct 22, 2019 Sent to Photo Copy
Oct 22, 2019 Modification Approved
Oct 28, 2019 Modification Request
Oct 28, 2019 Land Evidence Date
Oct 31, 2019 Bio Team Review for Completeness
Nov 05, 2019 Biologist Report
Nov 05, 2019 Typist for Processing
Nov 05, 2019 Executive Sign Off
Nov 05, 2019 Sent to Photo Copy
Nov 05, 2019 Modification Approved
Nov 07, 2019 HPHC Historical Preservation No Effect
Jan 14, 2020 Land Evidence Date
Jul 09, 2021 Modification Request
Jul 12, 2021 Administrative Review for Completeness
Jul 14, 2021 Eng Team Review for Completeness
Jul 14, 2021 Project Manager
Jul 16, 2021 Engineering Report
Jul 16, 2021 Letter of Authorization
Jul 19, 2021 Land Evidence Date
Jul 21, 2021 HPHC Review Pending
Jul 21, 2021 HPHC Historical Preservation No Effect
Jan 27, 2022 Modification Request
Jan 31, 2022 Administrative Review for Completeness
Feb 11, 2022 Project Manager
Feb 11, 2022 Bio Team Review for Completeness
Feb 15, 2022 Biologist Report
Feb 15, 2022 Typist for Processing
Feb 15, 2022 Executive Sign Off
Feb 15, 2022 Sent to Photo Copy
Feb 15, 2022 Letter of Authorization
Feb 18, 2022 Permit Mailed
Apr 07, 2022 Land Evidence Date

Details:

File No
2017-01-013
Town
East Providence
First Name
City of East Providence
Last Name
Street
0 Bold Point Park
Location
0 Bold Point Park
Plat/Map
6
Lot/Block
3
Decision Date
Feb 15, 2022
Dock Reg.No
Project
Extend for 2022; Temporary structures
Description
Other
Water Area
Easement
0
Acceptance Date
Oct 22, 2019