Action Date | Action Description |
---|---|
Jan 17, 2017 | Assent Application Received |
Jan 17, 2017 | Administrative Review for Completeness |
Jan 18, 2017 | Team Review for Completeness |
Jan 18, 2017 | Team Review for Completeness |
Jan 18, 2017 | Application Accepted |
Jan 27, 2017 | HPHC Historical Preservation No Effect |
Feb 01, 2017 | 30 day Public Notice Issued |
Feb 27, 2017 | Objections/Comments Received |
Mar 02, 2017 | Public Notice End Date |
Mar 06, 2017 | Plans Received |
Apr 10, 2017 | US Army Corps of Engineers Approval Received |
Apr 10, 2017 | Public Hearing Notices Mailed |
Apr 17, 2017 | Additional Information Received |
May 02, 2017 | Biologist Report |
May 02, 2017 | Engineering Report |
May 09, 2017 | Semi-Monthly Meeting Date Scheduled |
May 09, 2017 | Council Approval Granted |
Jul 24, 2017 | Stipulation Package from Biologist |
Jul 24, 2017 | Stipulation Package by Engineer |
Jul 26, 2017 | Typist for Processing |
Jul 26, 2017 | Category B assigned |
Jul 26, 2017 | Executive Sign Off |
Jul 26, 2017 | Sent to Photo Copy |
Jul 26, 2017 | Permit Approved |
Mar 05, 2018 | Modification Request |
Mar 06, 2018 | Administrative Review for Completeness |
Mar 06, 2018 | Team Review for Completeness |
Mar 06, 2018 | Application Accepted |
Mar 09, 2018 | HPHC Historical Preservation No Effect |
May 18, 2018 | Biologist Report |
May 18, 2018 | Typist for Processing |
May 18, 2018 | Executive Sign Off |
May 18, 2018 | Sent to Photo Copy |
May 18, 2018 | Modification Approved |
Jul 20, 2018 | Duplicate Original Assent requested/mailed |
May 15, 2019 | Land Evidence Date |
Aug 08, 2019 | Plans Received |