Action Date | Action Description |
---|---|
Jan 30, 2017 | Assent Application Received |
Feb 01, 2017 | Administrative Review for Completeness |
Feb 01, 2017 | Team Review for Completeness |
Feb 01, 2017 | Application Accepted |
Feb 16, 2017 | Biologist Report |
Feb 16, 2017 | Typist for Processing |
Feb 16, 2017 | Executive Sign Off |
Feb 16, 2017 | Sent to Photo Copy |
Feb 16, 2017 | Permit Approved |
Mar 03, 2017 | HPHC Historical Preservation No Effect |
Mar 20, 2017 | Land Evidence Date |