Action Date | Action Description |
---|---|
Feb 21, 2017 | Assent Application Received |
Feb 22, 2017 | Administrative Review for Completeness |
Feb 22, 2017 | Team Review for Completeness |
Feb 22, 2017 | Application Accepted |
Mar 22, 2017 | Plans Received |
Mar 24, 2017 | Biologist Report |
Mar 30, 2017 | Typist for Processing |
Mar 30, 2017 | Executive Sign Off |
Mar 30, 2017 | Sent to Photo Copy |
Mar 30, 2017 | Permit Approved |
Apr 05, 2017 | HPHC Historical Preservation No Effect |
Sep 17, 2018 | Modification Request |
Sep 18, 2018 | Administrative Review for Completeness |
Sep 19, 2018 | Team Review for Completeness |
Sep 19, 2018 | Application Accepted |
Sep 26, 2018 | Biologist Report |
Sep 26, 2018 | Typist for Processing |
Sep 26, 2018 | Modification Approved |
Oct 18, 2018 | HPHC Historical Preservation No Effect |