Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Feb 21, 2017 | Assent Application Received |
Feb 22, 2017 | Administrative Review for Completeness |
Feb 27, 2017 | Team Review for Completeness |
Feb 27, 2017 | Application Accepted |
Feb 27, 2017 | Category B assigned |
Mar 03, 2017 | HPHC Historical Preservation No Effect |
May 08, 2017 | US Army Corps of Engineers Approval Received |
May 12, 2017 | Dock/1.1.6 Review approval |
Jun 13, 2017 | Engineering Report |
Jun 13, 2017 | Typist for Processing |
Jun 13, 2017 | Executive Sign Off |
Jun 13, 2017 | Sent to Photo Copy |
Jun 13, 2017 | Permit Approved |
Jun 19, 2017 | Land Evidence Date |