Action Date | Action Description |
---|---|
Mar 01, 2017 | Assent Application Received |
Mar 06, 2017 | Administrative Review for Completeness |
Mar 07, 2017 | Team Review for Completeness |
Mar 07, 2017 | Application Accepted |
Mar 21, 2017 | 30 day Public Notice Issued |
Apr 04, 2017 | Plans Received |
Apr 21, 2017 | Typist for Processing |
Apr 21, 2017 | Executive Sign Off |
Apr 21, 2017 | Sent to Photo Copy |
Apr 21, 2017 | Permit Approved |
Apr 21, 2017 | Biologist Report |
Apr 21, 2017 | Public Notice End Date |
Apr 28, 2017 | Land Evidence Date |
May 08, 2017 | HPHC Historical Preservation No Effect |