Action Date | Action Description |
---|---|
Legal Response/Decision | |
Mar 01, 2017 | Assent Application Received |
Mar 06, 2017 | Administrative Review for Completeness |
Mar 13, 2017 | Team Review for Completeness |
Mar 13, 2017 | Application Accepted |
Mar 13, 2017 | 30 day Public Notice Issued |
Apr 13, 2017 | Public Notice End Date |
May 26, 2017 | Mail Agenda Notice |
Jun 09, 2017 | Continuance Requested |
Jun 09, 2017 | Continuance request by applicant granted by Director |
Jun 13, 2017 | Semi-Monthly Meeting Date Scheduled |
Oct 13, 2017 | Plans Received |
Oct 24, 2017 | Engineering Report |
Nov 30, 2017 | Ready to Schedule Semi-Monthly Meeting |
Jan 09, 2018 | Semi-Monthly Meeting Date Scheduled |
Jan 09, 2018 | Continued Application by the Council |
Jan 10, 2018 | Mail Agenda Notice |
Jan 23, 2018 | Council Approval Granted |
Jan 23, 2018 | Semi-Monthly Meeting Date Scheduled |
Feb 13, 2018 | Stipulation Package by Engineer |
Feb 14, 2018 | Typist for Processing |
Feb 14, 2018 | Executive Sign Off |
Feb 14, 2018 | Sent to Photo Copy |
Feb 14, 2018 | Permit Approved |
Mar 09, 2018 | Land Evidence Date |
Apr 26, 2018 | US Army Corps of Engineers Approval Received |