Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
HPHC Review Pending | |
Mar 09, 2017 | Assent Application Received |
Mar 10, 2017 | Administrative Review for Completeness |
Mar 13, 2017 | Team Review for Completeness |
Mar 13, 2017 | Deficient Application - Owner Notification Sent |
Mar 28, 2017 | Deficient Application Picked Up |
Aug 10, 2017 | Additional Information Received |
Aug 10, 2017 | Team Review for Completeness |
Aug 10, 2017 | Application Accepted |
Aug 11, 2017 | Category A* (Docks) |
Aug 11, 2017 | Assent Application Received |
Aug 11, 2017 | Administrative Review for Completeness |
Jan 26, 2018 | HPHC Historical Preservation No Effect |
Feb 16, 2018 | Plans Received |
Feb 20, 2018 | 30 day Public Notice Issued |
Mar 22, 2018 | Public Notice End Date |
Mar 30, 2018 | Public Notice End Date Extension Granted |
Mar 30, 2018 | Comments Received |
Apr 02, 2018 | Comments Received |
Apr 12, 2018 | Plans Received |
Apr 26, 2018 | Biologist Report |
May 02, 2018 | Dock/1.1.6 Review approval |
May 08, 2018 | Stipulation Package by Engineer |
May 08, 2018 | Permit Approved |
May 15, 2018 | Land Evidence Date |
Oct 01, 2019 | Correspondence Mailed/Faxed/E-mailed |
Apr 04, 2022 | Modification Request |
Apr 06, 2022 | Administrative Review for Completeness |
Apr 08, 2022 | Bio Team Review for Completeness |
Apr 21, 2022 | Deficient Application - Owner Notification Sent |
Apr 21, 2022 | Eng Team Review for Completeness |