Action Date | Action Description |
---|---|
Mar 15, 2017 | Assent Application Received |
Mar 15, 2017 | Administrative Review for Completeness |
Mar 16, 2017 | Team Review for Completeness |
Mar 16, 2017 | Application Accepted |
Apr 19, 2017 | HPHC Historical Preservation No Effect |
Apr 20, 2017 | Correspondence Mailed/Faxed/E-mailed |
May 10, 2017 | Additional Information Received |
May 10, 2017 | Biologist Report |
May 12, 2017 | Typist for Processing |
May 12, 2017 | Executive Sign Off |
May 12, 2017 | Sent to Photo Copy |
May 12, 2017 | Permit Approved |
May 22, 2017 | Land Evidence Date |