Action Date | Action Description |
---|---|
Mar 17, 2017 | Assent Application Received |
Mar 20, 2017 | Administrative Review for Completeness |
Mar 22, 2017 | Team Review for Completeness |
Mar 22, 2017 | Application Accepted |
Mar 24, 2017 | Plans Received |
Apr 28, 2017 | Biologist Report |
Apr 28, 2017 | HPHC Historical Preservation No Effect |
May 01, 2017 | Typist for Processing |
May 01, 2017 | Executive Sign Off |
May 01, 2017 | Sent to Photo Copy |
May 01, 2017 | Permit Approved |
May 03, 2017 | Land Evidence Date |