Action Date | Action Description |
---|---|
Mar 22, 2017 | Assent Application Received |
Mar 22, 2017 | Administrative Review for Completeness |
Mar 24, 2017 | Team Review for Completeness |
Mar 24, 2017 | Team Review for Completeness |
Mar 24, 2017 | Application Accepted |
Mar 24, 2017 | Category A* (Docks) |
Apr 06, 2017 | 30 day Public Notice Issued |
Apr 10, 2017 | HPHC Historical Preservation No Effect |
Apr 28, 2017 | Correspondence Mailed/Faxed/E-mailed |
May 06, 2017 | Public Notice End Date |
May 20, 2017 | Public Notice End Date Extension Granted |
May 22, 2017 | Objections/Comments Received |
May 31, 2017 | Meeting Held |
Jul 27, 2017 | Additional Information Received |
Jul 28, 2017 | Plans Received |
Nov 22, 2017 | Typist for Processing |
Nov 22, 2017 | Executive Sign Off |
Nov 22, 2017 | Sent to Photo Copy |
Nov 22, 2017 | Permit Approved |
Nov 22, 2017 | Biologist Report |
Nov 22, 2017 | Engineering Report |
Nov 30, 2017 | Land Evidence Date |
Mar 18, 2024 | Dock Post-Construction Certification by Engineer received. |