Action Date |
Action Description |
Mar 21, 2017 |
Dredge Application |
Mar 24, 2017 |
Administrative Review for Completeness |
Mar 28, 2017 |
Team Review for Completeness |
Mar 28, 2017 |
Application Accepted |
Mar 30, 2017 |
Category B assigned |
Apr 10, 2017 |
HPHC Historical Preservation No Effect |
Jul 27, 2017 |
Additional Information Received |
Sep 08, 2017 |
Additional Information Received |
Nov 03, 2017 |
Dredge Report |
Nov 08, 2017 |
DEM Dredge Permit |
Nov 08, 2017 |
Public Notice End Date Extension Granted |
Nov 17, 2017 |
Biologist Report |
Nov 17, 2017 |
Executive Signoff of Staff Reports |
Nov 30, 2017 |
Ready to Schedule Semi-Monthly Meeting |
Jan 09, 2018 |
Semi-Monthly Meeting Date Scheduled |
Jan 18, 2018 |
Council Approval Granted |
Jan 24, 2018 |
Legal Response/Decision |
Feb 05, 2018 |
Typist for Processing |
Feb 05, 2018 |
Executive Sign Off |
Feb 05, 2018 |
Sent to Photo Copy |
Feb 05, 2018 |
Permit Approved |
Feb 05, 2018 |
Stipulation Package from Biologist |
Feb 05, 2018 |
Stipulation Package by Engineer |
Feb 15, 2018 |
Land Evidence Date |
May 08, 2018 |
US Army Corps of Engineers Approval Received |
Aug 19, 2020 |
Modification Request |
Sep 08, 2020 |
Administrative Review for Completeness |
Sep 08, 2020 |
Eng Team Review for Completeness |
Sep 08, 2020 |
Project Manager |
Sep 09, 2020 |
15 day Public Notice Issued |
Sep 24, 2020 |
Public Notice End Date |
Sep 28, 2020 |
Objections/Comments Received |
Oct 02, 2020 |
Objections/Comments Received |
Oct 02, 2020 |
Objections/Comments Received |
Oct 02, 2020 |
Objections/Comments Received |
Oct 02, 2020 |
Public Notice End Date Extension Granted |
Oct 13, 2020 |
Objections/Comments Received |
Nov 27, 2020 |
Mail Agenda Notice |
Dec 02, 2020 |
CHA -- application modified due to CHA info |
Dec 02, 2020 |
Engineering Report |
Dec 02, 2020 |
Biologist Report |
Dec 07, 2020 |
Water Quality Certification |
Dec 08, 2020 |
Council Approval Granted |
Dec 08, 2020 |
Semi-Monthly Meeting Date Scheduled |
Dec 29, 2020 |
Stipulation Package by Engineer |
Dec 29, 2020 |
Stipulation Package from Biologist |
Dec 29, 2020 |
Legal Response/Decision |
Dec 29, 2020 |
30 Day Appeal Notification to Owner |
Dec 29, 2020 |
Modification Approved |
Jan 13, 2021 |
Land Evidence Date |
Jan 14, 2021 |
Monitoring Report |
Mar 02, 2022 |
US Army Corps of Engineers Approval Received |