Action Date | Action Description |
---|---|
Apr 03, 2017 | Assent Application Received |
Apr 04, 2017 | Administrative Review for Completeness |
Apr 04, 2017 | Team Review for Completeness |
Apr 04, 2017 | Application Accepted |
Apr 19, 2017 | HPHC Historical Preservation No Effect |
May 02, 2017 | Geologist Report |
May 02, 2017 | Typist for Processing |
May 02, 2017 | Executive Sign Off |
May 02, 2017 | Sent to Photo Copy |
May 02, 2017 | Permit Approved |