Action Date | Action Description |
---|---|
Apr 13, 2017 | Maintenance Certification Request |
Apr 14, 2017 | Administrative Review for Completeness |
Apr 25, 2017 | Team Review for Completeness |
Apr 25, 2017 | Application Accepted |
May 02, 2017 | Engineering Report |
May 02, 2017 | Typist for Processing |
May 02, 2017 | Executive Sign Off |
May 02, 2017 | Sent to Photo Copy |
May 02, 2017 | Permit Approved |
Dec 19, 2017 | Additional Information Received |