Action Date | Action Description |
---|---|
Ready to Schedule Semi-Monthly Meeting | |
Dec 02, 2016 | Assent Application Received |
Dec 02, 2016 | Administrative Review for Completeness |
Dec 22, 2016 | Team Review for Completeness |
Dec 22, 2016 | Application Accepted |
Mar 03, 2017 | Plans Received |
Apr 25, 2017 | Geologist Report |
May 04, 2017 | Mail Agenda Notice |
May 11, 2017 | Continued application |
May 12, 2017 | 30 day Public Notice Issued |
May 12, 2017 | Public Hearing Notices Mailed |
May 23, 2017 | Continued application |
May 23, 2017 | Semi-Monthly Meeting Date Scheduled |
Jun 05, 2017 | Objections/Comments Received |
Jun 12, 2017 | Public Notice End Date |
Jun 21, 2017 | Entry of Appearance Received |
Jun 27, 2017 | Continued Application by the Council |
Jun 27, 2017 | Semi-Monthly Meeting Date Scheduled |
Jul 10, 2017 | Ready to Schedule Semi-Monthly Meeting |
Jul 10, 2017 | Mail Agenda Notice |
Jul 25, 2017 | Continued Application by the Council |
Jul 25, 2017 | Semi-Monthly Meeting Date Scheduled |
Sep 18, 2017 | Typist for Processing |
Sep 18, 2017 | Executive Sign Off |
Sep 18, 2017 | Sent to Photo Copy |
Sep 18, 2017 | Permit Approved |