Action Date | Action Description |
---|---|
May 16, 2017 | Assent Application Received |
May 17, 2017 | Administrative Review for Completeness |
May 22, 2017 | Team Review for Completeness |
May 22, 2017 | Deficient Application - Owner Notification Sent |
Aug 08, 2017 | Deficiency Response Received |
Aug 11, 2017 | Team Review for Completeness |
Aug 11, 2017 | Application Accepted |
Aug 23, 2017 | HPHC Historical Preservation No Effect |
Aug 24, 2017 | 30 day Public Notice Issued |
Sep 25, 2017 | Public Notice End Date |
Nov 30, 2017 | Dock Meeting -- Approval |
Dec 06, 2017 | Biologist Report |
Dec 07, 2017 | Plans Received |
Dec 20, 2017 | Category B assigned |
Dec 20, 2017 | Executive Sign Off |
Dec 20, 2017 | Sent to Photo Copy |
Dec 20, 2017 | Permit Approved |
Dec 20, 2017 | Typist for Processing |
Feb 23, 2018 | Land Evidence Date |
May 02, 2019 | Dock Post-Construction Certification by Engineer received. |