Action Date | Action Description |
---|---|
Jul 11, 2017 | Maintenance Certification Request |
Jul 11, 2017 | Administrative Review for Completeness |
Jul 14, 2017 | Team Review for Completeness |
Jul 14, 2017 | Application Accepted |
Jul 26, 2017 | HPHC Historical Preservation No Effect |
Aug 02, 2017 | 30 day Public Notice Issued |
Sep 02, 2017 | Public Notice End Date |
Sep 19, 2017 | Geologist Report |
Sep 19, 2017 | Engineering Report |
Sep 19, 2017 | Typist for Processing |
Sep 19, 2017 | Executive Sign Off |
Sep 19, 2017 | Sent to Photo Copy |
Sep 19, 2017 | Permit Approved |
Dec 08, 2017 | Land Evidence Date |
Dec 08, 2017 | Water Quality Certification |
Dec 08, 2017 | US Army Corps of Engineers Approval Received |
May 29, 2018 | Additional Information Received |