Action Date | Action Description |
---|---|
Jul 26, 2017 | Assent Application Received |
Jul 27, 2017 | Administrative Review for Completeness |
Jul 28, 2017 | Team Review for Completeness |
Jul 28, 2017 | Application Accepted |
Jul 31, 2017 | Plans Received |
Aug 16, 2017 | HPHC Historical Preservation No Effect |
Aug 31, 2017 | Public Notice End Date |
Sep 15, 2017 | Biologist Report |
Sep 15, 2017 | Engineering Report |
Sep 20, 2017 | Plans Received |
Sep 26, 2017 | Mail Agenda Notice |
Oct 10, 2017 | Council Approval Granted |
Oct 10, 2017 | Semi-Monthly Meeting Date Scheduled |
Oct 12, 2017 | Legal Response/Decision |
Oct 16, 2017 | Typist for Processing |
Oct 16, 2017 | Stipulation Package from Biologist |
Oct 16, 2017 | Stipulation Package by Engineer |
Oct 17, 2017 | Executive Sign Off |
Oct 17, 2017 | Sent to Photo Copy |
Oct 17, 2017 | Permit Approved |
Oct 27, 2017 | Land Evidence Date |
Nov 27, 2017 | US Army Corps of Engineers Approval Received |
Jan 05, 2018 | Modification Request |
Jan 05, 2018 | Application Accepted |
Jan 08, 2018 | Biologist Report |
Jan 08, 2018 | Typist for Processing |
Jan 08, 2018 | Executive Sign Off |
Jan 08, 2018 | Sent to Photo Copy |
Jan 08, 2018 | Modification Approved |