Action Date | Action Description |
---|---|
Aug 10, 2017 | Assent Application Received |
Aug 11, 2017 | Administrative Review for Completeness |
Aug 11, 2017 | Team Review for Completeness |
Aug 11, 2017 | Application Accepted |
Aug 23, 2017 | HPHC Historical Preservation No Effect |
Jun 04, 2018 | Additional Information Received |
Jun 11, 2018 | Additional Information Received |
Oct 16, 2018 | Additional Information Received |
Oct 31, 2018 | Plans Received |
Nov 23, 2018 | Biologist Report |
Nov 26, 2018 | Typist for Processing |
Nov 26, 2018 | Executive Sign Off |
Nov 26, 2018 | Sent to Photo Copy |
Nov 26, 2018 | Permit Approved |
Jan 22, 2019 | Land Evidence Date |