Action Date | Action Description |
---|---|
Aug 28, 2017 | Assent Application Received |
Aug 28, 2017 | Administrative Review for Completeness |
Sep 12, 2017 | Team Review for Completeness |
Sep 12, 2017 | Application Accepted |
Sep 26, 2017 | HPHC Historical Preservation No Effect |
Oct 10, 2017 | Biologist Report |
Oct 12, 2017 | Typist for Processing |
Oct 12, 2017 | Executive Sign Off |
Oct 12, 2017 | Sent to Photo Copy |
Oct 12, 2017 | Permit Approved |
Nov 02, 2017 | Land Evidence Date |
Sep 13, 2018 | Modification Request |
Sep 13, 2018 | Administrative Review for Completeness |
Sep 17, 2018 | Team Review for Completeness |
Sep 17, 2018 | Application Accepted |
Oct 02, 2018 | HPHC Historical Preservation No Effect |
Oct 30, 2018 | Additional Information Requested from Applicant |
Nov 02, 2018 | Additional Information Received |
Nov 13, 2018 | Modification Approved |
Nov 13, 2018 | Biologist Report |
Dec 03, 2018 | Land Evidence Date |