Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Sep 06, 2017 | Assent Application Received |
Sep 06, 2017 | Administrative Review for Completeness |
Sep 07, 2017 | Team Review for Completeness |
Sep 07, 2017 | Application Accepted |
Sep 07, 2017 | Category A* (Docks) |
Sep 11, 2017 | Plans Received |
Sep 26, 2017 | HPHC Historical Preservation No Effect |
Oct 06, 2017 | 30 day Public Notice Issued |
Nov 06, 2017 | Public Notice End Date |
Nov 30, 2017 | Dock Meeting -- Approval |
Dec 05, 2017 | Typist for Processing |
Dec 05, 2017 | Executive Sign Off |
Dec 05, 2017 | Sent to Photo Copy |
Dec 05, 2017 | Permit Approved |
Dec 05, 2017 | Biologist Report |
Dec 13, 2017 | Land Evidence Date |
Jan 02, 2018 | US Army Corps of Engineers Approval Received |