Action Date | Action Description |
---|---|
Dec 11, 2017 | Assent Application Received |
Dec 11, 2017 | Administrative Review for Completeness |
Dec 12, 2017 | Team Review for Completeness |
Dec 12, 2017 | Application Accepted |
Jan 18, 2018 | Biologist Report |
Jan 18, 2018 | Typist for Processing |
Jan 18, 2018 | Executive Sign Off |
Jan 18, 2018 | Sent to Photo Copy |
Jan 18, 2018 | Permit Approved |
Jan 26, 2018 | Land Evidence Date |
May 09, 2018 | Modification Request |
May 10, 2018 | Administrative Review for Completeness |
May 10, 2018 | Plans Received |
May 10, 2018 | Team Review for Completeness |
May 10, 2018 | Application Accepted |
May 15, 2018 | Biologist Report |
May 15, 2018 | Typist for Processing |
May 15, 2018 | Executive Sign Off |
May 15, 2018 | Sent to Photo Copy |
May 15, 2018 | Modification Approved |
May 22, 2018 | HPHC Historical Preservation No Effect |
May 30, 2018 | Land Evidence Date |