Application 2017-12-040 Details

Back to List


Actions:

Action Date Action Description
Dec 12, 2017 Assent Application Received
Dec 12, 2017 Administrative Review for Completeness
Dec 13, 2017 Plans Received
Dec 14, 2017 Application Accepted
Dec 14, 2017 Category B assigned
Dec 14, 2017 Team Review for Completeness
Jan 08, 2018 30 day Public Notice Issued
Feb 08, 2018 Public Notice End Date
May 31, 2018 US Army Corps of Engineers Approval Received
Jun 20, 2018 Additional Information Received
Jun 21, 2018 Plans Received
Jun 21, 2018 HPHC Historical Preservation No Effect
Jun 22, 2018 Biologist Report
Jun 22, 2018 Engineering Report
Jun 22, 2018 Comments Received
Jun 25, 2018 Executive Signoff of Staff Reports
Jul 12, 2018 Ready to Schedule Semi-Monthly Meeting
Jul 12, 2018 Mail Agenda Notice
Jul 24, 2018 Council Approval Granted
Jul 24, 2018 Semi-Monthly Meeting Date Scheduled
Jul 30, 2018 Legal Response/Decision
Aug 27, 2018 Typist for Processing
Aug 27, 2018 Executive Sign Off
Aug 27, 2018 Sent to Photo Copy
Aug 27, 2018 Permit Approved
Aug 27, 2018 Stipulation Package from Biologist
Aug 27, 2018 Stipulation Package by Engineer
Aug 31, 2018 Land Evidence Date
Dec 05, 2018 Commencement of Work Notice received
Mar 12, 2019 Modification Request
Mar 12, 2019 Administrative Review for Completeness
Mar 13, 2019 Team Review for Completeness
Mar 13, 2019 Application Accepted
Mar 29, 2019 HPHC Review Pending
Mar 29, 2019 HPHC Historical Preservation No Effect
Apr 04, 2019 Biologist Report
Apr 08, 2019 Modification Approved
Apr 08, 2019 Typist for Processing
Apr 08, 2019 Executive Sign Off
Apr 08, 2019 Sent to Photo Copy
Apr 24, 2019 Land Evidence Date
Jun 28, 2019 Modification Request
Jun 28, 2019 Administrative Review for Completeness
Jul 01, 2019 Team Review for Completeness
Jul 01, 2019 Application Accepted
Jul 24, 2019 Biologist Report
Jul 24, 2019 Expiration of Assent/End of Tolling Legislation
Jul 24, 2019 Modification Approved
Apr 28, 2020 Correspondence Mailed/Faxed/E-mailed
Mar 18, 2021 Typist for Processing
Mar 18, 2021 Modification Approved
Mar 18, 2021 Extension Approved
Sep 13, 2022 Extension Approved
Feb 13, 2023 Correspondence Received
Mar 28, 2023 Extension Approved

Details:

File No
2017-12-040
Town
Providence
First Name
Narragansett Electric Company
Last Name
Street
South Street Seawall
Location
South Street Seawall
Plat/Map
21
Lot/Block
453
Decision Date
Aug 27, 2018
Dock Reg.No
Project
Rebuild existing seawall
Description
Shoreline Protection Facilities/Repair
Water Area
Easement
0
Acceptance Date
Jul 01, 2019