Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Mar 08, 2018 | Assent Application Received |
Mar 09, 2018 | Administrative Review for Completeness |
Mar 09, 2018 | Team Review for Completeness |
Mar 09, 2018 | Application Accepted |
Mar 20, 2018 | HPHC Historical Preservation No Effect |
Apr 25, 2018 | 30 day Public Notice Issued |
May 22, 2018 | Dock/1.1.6 Review approval |
May 24, 2018 | Biologist Report |
May 25, 2018 | Typist for Processing |
May 25, 2018 | Category A* (Docks) |
May 25, 2018 | Public Notice End Date |
May 25, 2018 | Permit Approved |
Jun 01, 2018 | US Army Corps of Engineers Approval Received |
Jun 22, 2018 | Land Evidence Date |
Dec 18, 2018 | Additional Information Received |