Application 2018-04-080 Details

Back to List


Actions:

Action Date Action Description
Apr 23, 2018 Assent Application Received
Apr 23, 2018 Team Review for Completeness
Apr 23, 2018 Team Review for Completeness
Apr 23, 2018 Application Accepted
May 04, 2018 Engineering Report
May 08, 2018 Stipulation Package by Engineer
May 08, 2018 Permit Approved
May 31, 2018 Land Evidence Date
Nov 29, 2018 HPHC Historical Preservation No Effect

Details:

File No
2018-04-080
Town
Providence
First Name
Narragansett Electric Company
Last Name
Street
Point Street Bridge
Location
Point Street Bridge
Plat/Map
Lot/Block
Decision Date
May 08, 2018
Dock Reg.No
Project
Providence River cable relocation project
Description
Utility Transmission (other than sewer)
Water Area
Easement
0
Acceptance Date
Apr 23, 2018