Action Date | Action Description |
---|---|
May 23, 2018 | Assent Application Received |
May 23, 2018 | Administrative Review for Completeness |
May 30, 2018 | Team Review for Completeness |
May 30, 2018 | Deficient Application - Owner Notification Sent |
Oct 17, 2018 | Deficiency Response Received |
Dec 07, 2018 | Team Review for Completeness |
Dec 07, 2018 | Application Accepted |
Jan 07, 2019 | HPHC Historical Preservation No Effect |
Jan 24, 2019 | 30 day Public Notice Issued |
Feb 24, 2019 | Public Notice End Date |
Mar 07, 2019 | Plans Received |
Apr 04, 2019 | Engineering Report |
Apr 08, 2019 | Typist for Processing |
Apr 08, 2019 | Executive Sign Off |
Apr 08, 2019 | Sent to Photo Copy |
Apr 08, 2019 | Permit Approved |
Apr 15, 2019 | Land Evidence Date |