Action Date | Action Description |
---|---|
Assent Requirement | |
Legal Response/Decision | |
Jul 17, 2018 | Assent Application Received |
Jul 17, 2018 | Administrative Review for Completeness |
Jul 27, 2018 | Plans Received |
Sep 10, 2018 | Application Accepted |
Sep 10, 2018 | Team Review for Completeness |
Sep 10, 2018 | Category B assigned |
Oct 03, 2018 | 30 day Public Notice Issued |
Oct 30, 2018 | Objections/Comments Received |
Nov 02, 2018 | Public Notice End Date |
Mar 06, 2019 | Plans Received |
Mar 07, 2019 | Supervisor Engineer SignOff |
Mar 07, 2019 | Supervisor Biologist SignOff |
Mar 07, 2019 | Engineering Report |
Mar 12, 2019 | Executive Signoff of Staff Reports |
Mar 15, 2019 | Ready to Schedule Semi-Monthly Meeting |
Mar 15, 2019 | Mail Agenda Notice |
Mar 22, 2019 | Continuance Requested |
Mar 25, 2019 | Management Review |
Mar 25, 2019 | Continuance request by applicant granted by Director |
Mar 26, 2019 | Semi-Monthly Meeting Date Scheduled |
Mar 29, 2019 | Ready to Schedule Semi-Monthly Meeting |
Mar 29, 2019 | Mail Agenda Notice |
Apr 09, 2019 | Semi-Monthly Meeting Date Scheduled |
Apr 23, 2019 | Council Approval Granted |
May 08, 2019 | Typist for Processing |
May 08, 2019 | Executive Sign Off |
May 08, 2019 | Sent to Photo Copy |
May 08, 2019 | Permit Approved |
May 20, 2019 | Land Evidence Date |