Action Date | Action Description |
---|---|
Sep 06, 2018 | Assent Application Received |
Sep 06, 2018 | Administrative Review for Completeness |
Sep 11, 2018 | Team Review for Completeness |
Sep 11, 2018 | Application Accepted |
Oct 01, 2018 | Engineering Report |
Oct 01, 2018 | Typist for Processing |
Oct 01, 2018 | Executive Sign Off |
Oct 01, 2018 | Sent to Photo Copy |
Oct 01, 2018 | Permit Approved |
Oct 02, 2018 | HPHC Historical Preservation No Effect |
Oct 16, 2018 | Duplicate Original Assent requested/mailed |
Oct 22, 2018 | Land Evidence Date |