Action Date | Action Description |
---|---|
HPHC Historical Preservation No Effect | |
Nov 13, 2018 | Assent Application Received |
Nov 13, 2018 | Administrative Review for Completeness |
Nov 14, 2018 | Team Review for Completeness |
Nov 14, 2018 | Application Accepted |
Feb 01, 2019 | Additional Information Received |
Feb 15, 2019 | 30 day Public Notice Issued |
Feb 26, 2019 | Letter of Authorization |
Mar 15, 2019 | Public Notice End Date |
Mar 19, 2019 | Plans Received |
Mar 22, 2019 | Typist for Processing |
Mar 22, 2019 | Executive Sign Off |
Mar 22, 2019 | Sent to Photo Copy |
Mar 22, 2019 | Permit Approved |
Mar 22, 2019 | Biologist Report |
Mar 22, 2019 | Engineering Report |
Mar 29, 2019 | Land Evidence Date |