Action Date | Action Description |
---|---|
Jan 15, 2019 | Assent Application Received |
Jan 15, 2019 | Administrative Review for Completeness |
Jan 17, 2019 | Team Review for Completeness |
Jan 17, 2019 | Application Accepted |
Feb 12, 2019 | Plans Received |
Mar 08, 2019 | Additional Information Received |
Mar 21, 2019 | Biologist Report |
Mar 21, 2019 | Engineering Report |
Mar 25, 2019 | Typist for Processing |
Mar 25, 2019 | Executive Sign Off |
Mar 25, 2019 | Sent to Photo Copy |
Mar 25, 2019 | Permit Approved |
May 10, 2019 | HPHC Historical Preservation No Effect |
May 10, 2019 | HPHC Review Pending |