Action Date | Action Description |
---|---|
Feb 05, 2019 | Assent Application Received |
Feb 05, 2019 | Administrative Review for Completeness |
Feb 06, 2019 | Team Review for Completeness |
Feb 06, 2019 | Application Accepted |
Feb 20, 2019 | HPHC Review Pending |
Feb 20, 2019 | HPHC Historical Preservation No Effect |
May 03, 2019 | Plans Received |
May 07, 2019 | Biologist Report |
May 08, 2019 | Typist for Processing |
May 08, 2019 | Executive Sign Off |
May 08, 2019 | Sent to Photo Copy |
May 08, 2019 | Permit Approved |
Jul 30, 2019 | Land Evidence Date |