Action Date | Action Description |
---|---|
Feb 14, 2019 | Assent Application Received |
Feb 14, 2019 | Administrative Review for Completeness |
Feb 20, 2019 | Team Review for Completeness |
Feb 20, 2019 | Application Accepted |
Mar 22, 2019 | Biologist Report |
Mar 22, 2019 | Typist for Processing |
Mar 22, 2019 | Executive Sign Off |
Mar 22, 2019 | Sent to Photo Copy |
Mar 29, 2019 | Permit Approved |
Mar 29, 2019 | HPHC Review Pending |
Mar 29, 2019 | HPHC Historical Preservation No Effect |
Apr 22, 2019 | Land Evidence Date |
Jan 11, 2022 | Extension of Permit Request |
Feb 09, 2022 | Enforcement Compliance Inspection Required |
Feb 22, 2022 | Process Extension |
Feb 22, 2022 | Extension Approved |
Mar 27, 2023 | Commencement of Work Notice received |