Action Date | Action Description |
---|---|
Jan 29, 2020 | Assent Application Received |
Jan 29, 2020 | Administrative Review for Completeness |
Jan 29, 2020 | Bio Team Review for Completeness |
Jan 29, 2020 | Application Accepted |
Feb 26, 2020 | HPHC Review Pending |
Feb 26, 2020 | HPHC Historical Preservation No Effect |
Mar 09, 2020 | Plans Received |
Mar 12, 2020 | Biologist Report |
Mar 16, 2020 | Typist for Processing |
Mar 16, 2020 | Executive Sign Off |
Mar 16, 2020 | Sent to Photo Copy |
Mar 16, 2020 | Permit Approved |
Mar 20, 2020 | Land Evidence Date |