Action Date | Action Description |
---|---|
Feb 25, 2020 | Assent Application Received |
Feb 25, 2020 | Administrative Review for Completeness |
Feb 27, 2020 | Eng Team Review for Completeness |
Feb 27, 2020 | Bio Team Review for Completeness |
Feb 27, 2020 | Engineering Report |
Feb 27, 2020 | Application Accepted |
Feb 27, 2020 | Finding Of No Significant Impact (FONSI) |
Mar 03, 2020 | Land Evidence Date |