Action Date | Action Description |
---|---|
US Army Corps of Engineers Approval Required | |
Dock Post-Construction Certification by Engineer received. | |
Jul 07, 2020 | Assent Application Received |
Jul 07, 2020 | Administrative Review for Completeness |
Jul 14, 2020 | Bio Team Review for Completeness |
Jul 14, 2020 | Deficient Application - Owner Notification Sent |
Jul 23, 2020 | Deficient Application Picked Up |
Aug 04, 2020 | Deficiency Response Received |
Aug 06, 2020 | Bio Team Review for Completeness |
Aug 06, 2020 | Application Accepted |
Aug 07, 2020 | Project Manager |
Aug 07, 2020 | Category A* (Docks) |
Aug 11, 2020 | Plans Received |
Aug 31, 2020 | HPHC Historical Preservation No Effect |
Aug 31, 2020 | HPHC Review Pending |
Oct 19, 2020 | 30 day Public Notice Issued |
Nov 18, 2020 | Dock Meeting -- Approval |
Nov 19, 2020 | Public Notice End Date |
Nov 23, 2020 | Biologist Report |
Nov 23, 2020 | Stipulation Package from Biologist |
Nov 23, 2020 | Typist for Processing |
Nov 23, 2020 | Executive Sign Off |
Nov 23, 2020 | Sent to Photo Copy |
Nov 23, 2020 | Permit Approved |
Dec 11, 2020 | Land Evidence Date |
Dec 15, 2020 | Additional Information Received |