Action Date | Action Description |
---|---|
Aug 21, 2020 | Assent Application Received |
Sep 11, 2020 | Administrative Review for Completeness |
Sep 14, 2020 | Eng Team Review for Completeness |
Sep 14, 2020 | Bio Team Review for Completeness |
Sep 14, 2020 | Project Manager |
Sep 14, 2020 | Application Accepted |
Oct 06, 2020 | HPHC Historical Preservation No Effect |
Oct 06, 2020 | HPHC Review Pending |
Oct 08, 2020 | Plans Received |
Oct 09, 2020 | Biologist Report |
Oct 09, 2020 | Engineering Report |
Oct 13, 2020 | Typist for Processing |
Oct 13, 2020 | Executive Sign Off |
Oct 13, 2020 | Sent to Photo Copy |
Oct 13, 2020 | Permit Approved |
Oct 13, 2020 | Project Manager |
Nov 09, 2020 | Land Evidence Date |
Mar 02, 2023 | Modification Request |
Mar 09, 2023 | Administrative Review for Completeness |
Mar 13, 2023 | Bio Team Review for Completeness |
Mar 13, 2023 | Project Manager |
Mar 24, 2023 | HPHC Historical Preservation No Effect |
Apr 25, 2023 | Biologist Report |
May 03, 2023 | Typist for Processing |
May 03, 2023 | Executive Sign Off |
May 03, 2023 | Sent to Photo Copy |
May 03, 2023 | Modification Approved |
May 05, 2023 | Permit Mailed |