Action Date | Action Description |
---|---|
Sep 16, 2020 | Assent Application Received |
Sep 22, 2020 | Administrative Review for Completeness |
Sep 22, 2020 | Category A* (Docks) |
Nov 02, 2020 | Additional Information Received |
Nov 04, 2020 | Application Accepted |
Nov 04, 2020 | Project Manager |
Nov 04, 2020 | Bio Team Review for Completeness |
Nov 09, 2020 | 30 day Public Notice Issued |
Nov 18, 2020 | Dock Meeting -- Approval |
Nov 25, 2020 | HPHC Historical Preservation No Effect |
Nov 25, 2020 | HPHC Review Pending |
Dec 09, 2020 | Public Notice End Date |
Dec 14, 2020 | Plans Received |
Dec 18, 2020 | Stipulation Package from Biologist |
Dec 18, 2020 | Typist for Processing |
Dec 18, 2020 | Executive Sign Off |
Dec 18, 2020 | Sent to Photo Copy |
Dec 18, 2020 | Permit Approved |
Dec 18, 2020 | Biologist Report |
Dec 22, 2020 | US Army Corps of Engineers Approval Received |
Jan 06, 2021 | Land Evidence Date |
Feb 08, 2022 | Note to File |
Feb 08, 2022 | Modification Request |
Feb 14, 2022 | Administrative Review for Completeness |
Feb 15, 2022 | Bio Team Review for Completeness |
Feb 15, 2022 | Project Manager |
Feb 16, 2022 | Biologist Report |
Feb 21, 2022 | Typist for Processing |
Feb 21, 2022 | Executive Sign Off |
Feb 21, 2022 | Sent to Photo Copy |
Feb 21, 2022 | Modification Approved |
Feb 23, 2022 | Permit Mailed |
Mar 02, 2022 | HPHC Review Pending |
Mar 02, 2022 | HPHC Historical Preservation No Effect |
Mar 07, 2022 | Land Evidence Date |