Action Date | Action Description |
---|---|
Enforcement Compliance Inspection Required | |
Oct 14, 2020 | Assent Application Received |
Oct 14, 2020 | Administrative Review for Completeness |
Oct 15, 2020 | Eng Team Review for Completeness |
Oct 15, 2020 | Bio Team Review for Completeness |
Oct 15, 2020 | Project Manager |
Oct 15, 2020 | Application Accepted |
Oct 27, 2020 | HPHC Historical Preservation No Effect |
Oct 27, 2020 | HPHC Review Pending |
Nov 09, 2020 | Engineering Report |
Nov 09, 2020 | Stipulation Package by Engineer |
Nov 09, 2020 | Typist for Processing |
Nov 09, 2020 | Executive Sign Off |
Nov 09, 2020 | Sent to Photo Copy |
Nov 09, 2020 | Permit Approved |
Nov 10, 2020 | Stipulation Package from Biologist |
Nov 10, 2020 | Biologist Report |
Dec 14, 2020 | Land Evidence Date |
Aug 30, 2023 | Extension of Permit Request |
Nov 29, 2023 | Enforcement Compliance Inspection Required |
Nov 30, 2023 | Process Extension |
Nov 30, 2023 | Typist for Processing |
Nov 30, 2023 | Executive Sign Off |
Nov 30, 2023 | Sent to Photo Copy |
Nov 30, 2023 | Extension Approved |
Sep 06, 2024 | Extension of Permit Request |