Action Date | Action Description |
---|---|
Assent Requirement | |
Feb 17, 2021 | Assent Application Received |
Feb 17, 2021 | Administrative Review for Completeness |
Mar 05, 2021 | Additional Information Requested from Applicant |
Mar 22, 2021 | Additional Information Received |
Apr 16, 2021 | Application Accepted |
Apr 16, 2021 | Bio Team Review for Completeness |
Apr 17, 2021 | Project Manager |
Apr 19, 2021 | Additional Information Requested from Applicant |
Apr 30, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 03, 2021 | Correspondence Received |
May 04, 2021 | Additional Information Received |
May 05, 2021 | Additional Information Requested from Applicant |
May 06, 2021 | Correspondence Received |
May 11, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 12, 2021 | Note to File |
May 12, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 12, 2021 | Correspondence Received |
May 19, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 19, 2021 | Correspondence Received |
May 27, 2021 | Correspondence Received |
May 28, 2021 | Correspondence Received |
May 28, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jun 16, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jul 07, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jul 09, 2021 | Correspondence Received |
Jul 12, 2021 | Correspondence Mailed/Faxed/E-mailed |
Aug 10, 2021 | Plans Received |
Sep 03, 2021 | Site Inspection |
Sep 03, 2021 | Correspondence Mailed/Faxed/E-mailed |
Sep 14, 2021 | Plans Received |
Sep 16, 2021 | Note to File |
Sep 22, 2021 | Additional Information Requested from Applicant |
Sep 27, 2021 | Land Evidence Date |
Oct 19, 2021 | Plans Received |
Oct 20, 2021 | Biologist Report |
Oct 21, 2021 | Typist for Processing |
Oct 21, 2021 | Permit Approved |
Oct 26, 2021 | HPHC Review Pending |
Oct 26, 2021 | HPHC Historical Preservation No Effect |
Oct 27, 2021 | Permit Mailed |
Jan 24, 2022 | Land Evidence Date |