Action Date | Action Description |
---|---|
Mar 23, 2021 | Assent Application Received |
Mar 24, 2021 | Administrative Review for Completeness |
Mar 29, 2021 | Category B assigned |
Mar 29, 2021 | Bio Team Review for Completeness |
Mar 29, 2021 | Application Accepted |
Mar 29, 2021 | Project Manager |
Apr 13, 2021 | HPHC Review Pending |
Apr 13, 2021 | 30 day Public Notice Issued |
Apr 13, 2021 | HPHC Historical Preservation No Effect |
May 11, 2021 | Comments Received |
May 13, 2021 | Public Notice End Date |
Jul 23, 2021 | Additional Information Requested from Applicant |
Aug 10, 2021 | Meeting Held |
Aug 10, 2021 | Review on Hold |
Mar 16, 2022 | Additional Information Received |
May 04, 2022 | Note to File |
May 09, 2022 | Additional Information Requested from Applicant |
May 25, 2022 | Meeting Held |
Jun 20, 2022 | Additional Information Received |
Jun 22, 2022 | Correspondence Mailed/Faxed/E-mailed |
Jun 22, 2022 | Additional Information Received |
Sep 27, 2022 | Additional Information Received |
Nov 29, 2022 | Additional Information Requested from Applicant |
Jan 06, 2023 | Additional Information Received |
Feb 10, 2023 | Phone Call |
Feb 15, 2023 | Mail Agenda Notice |
Feb 22, 2023 | Biologist Report |
Feb 22, 2023 | Engineering Report |
Feb 23, 2023 | Executive Signoff of Staff Reports |
Feb 28, 2023 | Continued Application by the Council |
Feb 28, 2023 | Semi-Monthly Meeting Date Scheduled |
Mar 06, 2023 | Mail Agenda Notice |
Mar 14, 2023 | Semi-Monthly Meeting Date Scheduled |
Mar 24, 2023 | Continued application |
Mar 28, 2023 | Semi-Monthly Meeting Date Scheduled |
Apr 04, 2023 | Mail Agenda Notice |
Apr 24, 2023 | Council Approval Granted |
Apr 24, 2023 | Semi-Monthly Meeting Date Scheduled |
Aug 31, 2023 | Correspondence Received |
Sep 06, 2023 | Legal Response/Decision |
Sep 14, 2023 | Typist for Processing |
Sep 14, 2023 | Executive Sign Off |
Sep 14, 2023 | Sent to Photo Copy |
Sep 14, 2023 | Permit Approved |
Sep 14, 2023 | Stipulation Package from Biologist |
Sep 14, 2023 | Stipulation Package by Engineer |
Sep 18, 2023 | Permit Mailed |
Sep 22, 2023 | Land Evidence Date |