Action Date | Action Description |
---|---|
Apr 23, 2021 | Assent Application Received |
Apr 23, 2021 | Administrative Review for Completeness |
May 05, 2021 | Eng Team Review for Completeness |
May 05, 2021 | Application Accepted |
May 05, 2021 | Project Manager |
May 17, 2021 | HPHC Historical Preservation No Effect |
May 17, 2021 | HPHC Review Pending |
May 25, 2021 | 30 day Public Notice Issued |
Jun 25, 2021 | Public Notice End Date |
Oct 14, 2021 | Dock/1.1.6 Review approval |
Dec 07, 2021 | Engineering Report |
Dec 13, 2021 | Typist for Processing |
Dec 13, 2021 | Permit Approved |
Dec 13, 2021 | Executive Sign Off |
Dec 13, 2021 | Sent to Photo Copy |
Dec 17, 2021 | Permit Mailed |
Dec 22, 2021 | Land Evidence Date |
Jul 10, 2023 | Dock Post-Construction Certification by Engineer received. |
Jan 03, 2024 | Modification Request |
Mar 29, 2024 | 30 day Public Notice Issued |
Apr 29, 2024 | Public Notice End Date |
May 01, 2024 | Engineering Report |
May 02, 2024 | Typist for Processing |
May 02, 2024 | Executive Sign Off |
May 02, 2024 | Modification Approved |
May 24, 2024 | Land Evidence Date |