Action Date | Action Description |
---|---|
Aug 27, 2013 | Assent Application Received |
Aug 27, 2013 | Administrative Review for Completeness |
Oct 03, 2013 | Team Review for Completeness |
Oct 03, 2013 | Application Accepted |
Dec 04, 2013 | Additional Information Received |
Dec 19, 2013 | Plans Received |
Jan 02, 2014 | Engineering Report |
Jan 02, 2014 | Biologist Report |
Jan 03, 2014 | Typist for Processing |
Jan 03, 2014 | Permit Approved |
Jan 06, 2014 | Executive Sign Off |
Jan 06, 2014 | Sent to Photo Copy |
Jan 16, 2014 | HPHC Historical Preservation No Effect |
Jan 17, 2014 | Land Evidence Date |
Jan 31, 2014 | Water Quality Certification |
Nov 29, 2017 | Modification Request |
Nov 29, 2017 | Administrative Review for Completeness |
Nov 30, 2017 | Team Review for Completeness |
Nov 30, 2017 | Application Accepted |
Dec 18, 2017 | Biologist Report |
Dec 18, 2017 | Typist for Processing |
Dec 18, 2017 | Executive Sign Off |
Dec 18, 2017 | Sent to Photo Copy |
Dec 18, 2017 | Modification Approved |
Jan 08, 2018 | HPHC Historical Preservation No Effect |
Mar 07, 2018 | Duplicate Original Assent requested/mailed |
Mar 09, 2018 | Land Evidence Date |
Mar 20, 2019 | Extension of Permit Request |
Apr 25, 2019 | Enforcement Compliance Inspection Required |
Apr 25, 2019 | Process Extension |
Apr 25, 2019 | Extension Approved |
May 04, 2020 | Extension of Permit Request |
Jun 02, 2020 | Enforcement Compliance Inspection Required |
Jun 03, 2020 | Process Extension |
Jun 03, 2020 | Extension Approved |
Apr 13, 2021 | Extension of Permit Request |
May 03, 2021 | Category A assigned |
Jul 12, 2021 | Enforcement Compliance Inspection Required |
Jul 27, 2021 | Semi-Monthly Meeting Date Scheduled |
Jul 27, 2021 | Council Approval - Extension Granted |
Aug 24, 2021 | Extension Approved |
Aug 24, 2021 | Process Extension |