Action Date | Action Description |
---|---|
Jun 21, 2021 | Assent Application Received |
Jun 24, 2021 | Administrative Review for Completeness |
Jun 28, 2021 | Eng Team Review for Completeness |
Jun 28, 2021 | Bio Team Review for Completeness |
Jun 28, 2021 | Project Manager |
Jun 28, 2021 | Application Accepted |
Jul 26, 2021 | 30 day Public Notice Issued |
Jul 26, 2021 | Comments Received |
Jul 30, 2021 | HPHC Historical Preservation Comments/Concerns |
Aug 13, 2021 | Comments Received |
Aug 26, 2021 | Public Notice End Date |
Sep 17, 2021 | HPHC Historical Preservation No Effect |
Sep 27, 2021 | Comments Received |
Sep 27, 2021 | Public Notice End Date Extension Granted |
Sep 29, 2021 | Comments Received |
Sep 30, 2021 | Additional Information Requested from Applicant |
Oct 01, 2021 | Correspondence Mailed/Faxed/E-mailed |
Oct 01, 2021 | Memorandum of Agreement signed |
Oct 01, 2021 | CHA Worksheet received |
Nov 01, 2021 | Objection withdrawal received |
Dec 21, 2021 | Plans Received |
Dec 23, 2021 | Engineering Report |
Dec 23, 2021 | Biologist Report |
Jan 05, 2022 | Permit Approved |
Jan 05, 2022 | Typist for Processing |
Jan 07, 2022 | Permit Mailed |
Jan 18, 2022 | Land Evidence Date |
Jan 24, 2022 | Water Quality Certification |