Image not found

Application 2021-07-005 Details

Back to List


Actions:

Action Date Action Description
Jul 01, 2021 Assent Application Received
Jul 20, 2021 Note to File
Jul 23, 2021 Category B assigned
Jul 31, 2021 Additional Information Received
Aug 10, 2021 Application Accepted
Aug 10, 2021 Project Manager
Aug 10, 2021 Eng Team Review for Completeness
Aug 10, 2021 Eng Team Review for Completeness
Oct 15, 2021 Joint Public Notice
Nov 29, 2021 Comments Received
Dec 14, 2021 Comments Received
Dec 15, 2021 Comments Received
Dec 15, 2021 Public Notice End Date
Jan 25, 2022 HPHC Review Pending
Jan 25, 2022 HPHC Historical Preservation No Effect
Feb 16, 2022 Objections/Comments Received
Mar 15, 2022 Additional Information Received
Mar 22, 2022 Correspondence Received
Mar 24, 2022 Additional Information Received
Apr 18, 2022 Additional Information Received
Apr 25, 2022 Additional Information Received
Sep 22, 2022 Engineering Report
Oct 25, 2022 Engineering Report
Oct 31, 2022 Objections/Comments Received
Oct 31, 2022 Objections/Comments Received
Nov 01, 2022 Semi-Monthly Meeting Held
Nov 14, 2022 Additional Information Received
Nov 15, 2022 Additional Information Received
Nov 22, 2022 Semi-Monthly Meeting Held
Dec 13, 2022 Semi-Monthly Meeting Held
Feb 08, 2023 Legal Response/Decision
Feb 08, 2023 30 Day Appeal Notification to Owner
Feb 21, 2023 30 Day Appeal Notification to Owner
Feb 21, 2023 Legal Response/Decision
Mar 13, 2023 Typist for Processing
Mar 13, 2023 Permit Approved
Mar 15, 2023 Permit Mailed
Jun 20, 2023 Mail Agenda Notice
Jun 27, 2023 Semi-Monthly Meeting Date Scheduled
Jul 03, 2023 Land Evidence Date
Jul 26, 2023 Letter of Authorization
Aug 25, 2023 Land Evidence Date
Dec 01, 2023 Modification Request
Dec 06, 2023 Administrative Review for Completeness
Dec 14, 2023 Assent Amended
Dec 18, 2023 Permit Mailed
Dec 19, 2023 HPHC Historical Preservation No Effect
Dec 29, 2023 Land Evidence Date
Jun 27, 2024 Correspondence Received

Details:

File No
2021-07-005
Town
North Kingstown
First Name
LLC
Last Name
Revolution Wind
Street
& 594 Camp Ave, 135 Circuit Dr
Location
574 & 594 Camp Ave, 135 Circuit Dr, 244
Plat/Map
179|185
Lot/Block
1,11,30|1,4,8
Decision Date
Jul 26, 2023
Dock Reg.No
Project
Export cable; 2 underground transition joint bays to connect RWEC-RI cable; substation
Description
Other
Water Area
Easement
0
Acceptance Date
Aug 10, 2021

Back to List