Action Date | Action Description |
---|---|
Jul 22, 2021 | Assent Application Received |
Jul 27, 2021 | Administrative Review for Completeness |
Jul 27, 2021 | CHA Worksheet received |
Jul 29, 2021 | Bio Team Review for Completeness |
Jul 29, 2021 | Deficient Application - Owner Notification Sent |
Nov 02, 2021 | Deficient Application Picked Up |
Jan 10, 2022 | Deficiency Response Received |
Jan 20, 2022 | Bio Team Review for Completeness |
Jan 20, 2022 | Application Accepted |
Jan 20, 2022 | Project Manager |
Jan 31, 2022 | Additional Information Requested from Applicant |
Feb 16, 2022 | HPHC Historical Preservation Comments/Concerns |
Feb 16, 2022 | HPHC Review Pending |
Mar 17, 2022 | Correspondence Received |
Mar 17, 2022 | Correspondence Mailed/Faxed/E-mailed |
Mar 22, 2022 | HPHC Historical Preservation No Effect |
Apr 27, 2022 | Permit Approved |
Apr 27, 2022 | Permit Mailed |
Apr 27, 2022 | Typist for Processing |
Apr 27, 2022 | Biologist Report |
Apr 27, 2022 | Engineering Report |
Apr 29, 2022 | Permit Mailed |
Jan 12, 2023 | Land Evidence Date |