Action Date | Action Description |
---|---|
Aug 02, 2021 | Assent Application Received |
Aug 06, 2021 | Administrative Review for Completeness |
Aug 06, 2021 | CHA Worksheet received |
Aug 17, 2021 | Deficiency - Phone Call to Applicant/Owner |
Oct 18, 2021 | Deficient Application - Owner Notification Sent |
Oct 18, 2021 | Bio Team Review for Completeness |
Nov 01, 2021 | Deficiency Response Received |
Nov 12, 2021 | Administrative Review for Completeness |
Nov 16, 2021 | Bio Team Review for Completeness |
Nov 16, 2021 | Application Accepted |
Nov 16, 2021 | Project Manager |
Dec 09, 2021 | HPHC Historical Preservation Comments/Concerns |
Dec 09, 2021 | HPHC Review Pending |
May 24, 2022 | Additional Information Requested from Applicant |
Oct 27, 2023 | HPHC Historical Preservation No Effect |
Oct 30, 2023 | Biologist Report |
Oct 31, 2023 | Typist for Processing |
Oct 31, 2023 | Executive Sign Off |
Oct 31, 2023 | Sent to Photo Copy |
Oct 31, 2023 | Permit Approved |
Nov 01, 2023 | Permit Mailed |
Nov 17, 2023 | Land Evidence Date |