Image not found

Application 2021-08-079 Details

Back to List


Actions:

Action Date Action Description
Aug 19, 2021 Maintenance Certification Request
Aug 19, 2021 Administrative Review for Completeness
Aug 20, 2021 Bio Team Review for Completeness
Aug 31, 2021 Team Review for Completeness
Aug 31, 2021 Application Accepted
Aug 31, 2021 Project Manager
Sep 01, 2021 Engineering Report
Sep 02, 2021 Permit Approved
Sep 03, 2021 HPHC Historical Preservation No Effect
Sep 08, 2021 Permit Mailed
Apr 15, 2022 Correspondence Received
Apr 27, 2022 Letter of Authorization

Details:

File No
2021-08-079
Town
New England Tidal Waters
First Name
The Narragansett Electric Comp
Last Name
Street
Utility Maintenance Activities
Location
Utility Maintenance Activities
Plat/Map
Lot/Block
Decision Date
Apr 27, 2022
Dock Reg.No
Project
Replace and repair utility poles on the existing overhead electric 3302 subtransmission line. As pe
Description
Maintenance (Residential/Commercial)
Water Area
Easement
0
Acceptance Date
Aug 31, 2021

Back to List