Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Aug 19, 2021 | Assent Application Received |
Aug 24, 2021 | Administrative Review for Completeness |
Aug 31, 2021 | Bio Team Review for Completeness |
Sep 01, 2021 | Deficient Application - Owner Notification Sent |
Sep 24, 2021 | Deficiency Response Received |
Sep 28, 2021 | Bio Team Review for Completeness |
Sep 28, 2021 | Application Accepted |
Sep 29, 2021 | Project Manager |
Sep 29, 2021 | Category B assigned |
Sep 30, 2021 | Plans Received |
Oct 13, 2021 | HPHC Review Pending |
Oct 13, 2021 | HPHC Historical Preservation No Effect |
Oct 20, 2021 | 30 day Public Notice Issued |
Nov 20, 2021 | Public Notice End Date |
Jan 12, 2022 | Engineering Report |
Jan 21, 2022 | Typist for Processing |
Jan 21, 2022 | Executive Sign Off |
Jan 21, 2022 | Sent to Photo Copy |
Jan 21, 2022 | Permit Approved |
Jan 24, 2022 | Permit Mailed |
Aug 10, 2022 | Land Evidence Date |