Action Date | Action Description |
---|---|
Aug 27, 2021 | Assent Application Received |
Sep 02, 2021 | Administrative Review for Completeness |
Sep 08, 2021 | Bio Team Review for Completeness |
Sep 09, 2021 | Deficient Application - Owner Notification Sent |
Apr 01, 2022 | Deficiency Response Received |
Apr 15, 2022 | Bio Team Review for Completeness |
Apr 15, 2022 | Project Manager |
Apr 18, 2022 | Application Accepted |
May 11, 2022 | HPHC Review Pending |
May 11, 2022 | HPHC Historical Preservation No Effect |
Oct 11, 2022 | Additional Information Received |
Oct 17, 2022 | Biologist Report |
Oct 24, 2022 | Permit Mailed |
Oct 24, 2022 | Typist for Processing |
Oct 24, 2022 | Executive Sign Off |
Oct 24, 2022 | Sent to Photo Copy |
Oct 24, 2022 | Permit Approved |
Jan 27, 2023 | Land Evidence Date |