Action Date | Action Description |
---|---|
Permit Mailed | |
Sep 17, 2021 | Assent Application Received |
Sep 21, 2021 | Administrative Review for Completeness |
Sep 23, 2021 | Bio Team Review for Completeness |
Sep 23, 2021 | Application Accepted |
Sep 29, 2021 | Project Manager |
Oct 08, 2021 | Additional Information Received |
Oct 13, 2021 | Biologist Report |
Oct 13, 2021 | HPHC Review Pending |
Oct 13, 2021 | HPHC Historical Preservation No Effect |
Oct 18, 2021 | Stipulation Package from Biologist |
Oct 18, 2021 | Typist for Processing |
Oct 18, 2021 | Executive Sign Off |
Oct 18, 2021 | Sent to Photo Copy |
Oct 18, 2021 | Permit Approved |
Aug 30, 2022 | Duplicate Original Assent requested/mailed |
Oct 11, 2022 | Land Evidence Date |